Drilling Archives - طراحی سایت | سئو و بهینه سازی سایت | سامانه پیامکی|تدبیرنت https://www.tadbirnet.ir/portfolio_cat/drilling/ Another WordPress site Sat, 19 Oct 2019 07:12:42 +0000 en-US hourly 1 https://wordpress.org/?v=6.2.5 https://www.tadbirnet.ir/file/uploads/2019/11/cropped-themento-192x192-32x32.png Drilling Archives - طراحی سایت | سئو و بهینه سازی سایت | سامانه پیامکی|تدبیرنت https://www.tadbirnet.ir/portfolio_cat/drilling/ 32 32 Project one https://www.tadbirnet.ir/portfolio/project-one-2/ https://www.tadbirnet.ir/portfolio/project-one-2/#respond Mon, 01 Apr 2019 16:19:30 +0000 https://www.tadbirnet.ir/?post_type=portfolio&p=1434 Objectives of the project: Phase 1: Handling 50,000 barrels of oil and injected 70 million cubic feet of gas a day Phase 2: Achieve 110,000 barrels of oil and inject 210 million cubic feet of gas a day Geographical location of the project: km north of Khorramshahr and 100 km southwest of Ahwaz, along the […]

The post Project one appeared first on طراحی سایت | سئو و بهینه سازی سایت | سامانه پیامکی|تدبیرنت.

]]>
slide-2feca5b
slide-f145459
slide-444258c
slide-f4fec89

Objectives of the project:

Phase 1: Handling 50,000 barrels of oil and injected 70 million cubic feet of gas a day

Phase 2: Achieve 110,000 barrels of oil and inject 210 million cubic feet of gas a day

Geographical location of the project:

km north of Khorramshahr and 100 km southwest of Ahwaz, along the Ahwaz-Khorramshahr road

main contractor:

Phase 1 and 2 ENI / NICO

Project Implementation Activities:

Drilling of 3 wells and 5 wells and one well gas injection well The creation of a unit of operation with a nominal capacity of 55 thousand barrels per day All pipelines and pipelines in the first phase of the project Drilling 15 development loops, 3 gas injection wells and one wells water disposal Zayed, along with the creation of a unit of operation with a nominal capacity of 165 thousand barrels of oil On the day, including all lines of flow and well-developed facilities in the second phase

– Feasibility Study Phase III was conducted by ENI

– Define the descriptive stage of the design and preparation of documents for this part of the work using internal resources

Key layout times:

Date of Contract Entry: April 13,

Production of 50,000 barrels per day will be achieved on August 83

Production forecast reached 160 thousand barrels per day: September, 2002

Forecast of gas injection at 280 million cubic feet per day: Spring 2010

The post Project one appeared first on طراحی سایت | سئو و بهینه سازی سایت | سامانه پیامکی|تدبیرنت.

]]>
https://www.tadbirnet.ir/portfolio/project-one-2/feed/ 0
Project Six https://www.tadbirnet.ir/portfolio/project-six/ https://www.tadbirnet.ir/portfolio/project-six/#respond Sun, 31 Mar 2019 20:38:23 +0000 https://www.tadbirnet.ir/?post_type=portfolio&p=1422 Objectives of the project: Phase 1: Handling 50,000 barrels of oil and injected 70 million cubic feet of gas a day Phase 2: Achieve 110,000 barrels of oil and inject 210 million cubic feet of gas a day Geographical location of the project: km north of Khorramshahr and 100 km southwest of Ahwaz, along the […]

The post Project Six appeared first on طراحی سایت | سئو و بهینه سازی سایت | سامانه پیامکی|تدبیرنت.

]]>
slide-2feca5b
slide-f145459
slide-444258c
slide-f4fec89

Objectives of the project:

Phase 1: Handling 50,000 barrels of oil and injected 70 million cubic feet of gas a day

Phase 2: Achieve 110,000 barrels of oil and inject 210 million cubic feet of gas a day

Geographical location of the project:

km north of Khorramshahr and 100 km southwest of Ahwaz, along the Ahwaz-Khorramshahr road

main contractor:

Phase 1 and 2 ENI / NICO

Project Implementation Activities:

Drilling of 3 wells and 5 wells and one well gas injection well The creation of a unit of operation with a nominal capacity of 55 thousand barrels per day All pipelines and pipelines in the first phase of the project Drilling 15 development loops, 3 gas injection wells and one wells water disposal Zayed, along with the creation of a unit of operation with a nominal capacity of 165 thousand barrels of oil On the day, including all lines of flow and well-developed facilities in the second phase

– Feasibility Study Phase III was conducted by ENI

– Define the descriptive stage of the design and preparation of documents for this part of the work using internal resources

Key layout times:

Date of Contract Entry: April 13,

Production of 50,000 barrels per day will be achieved on August 83

Production forecast reached 160 thousand barrels per day: September, 2002

Forecast of gas injection at 280 million cubic feet per day: Spring 2010

The post Project Six appeared first on طراحی سایت | سئو و بهینه سازی سایت | سامانه پیامکی|تدبیرنت.

]]>
https://www.tadbirnet.ir/portfolio/project-six/feed/ 0
Project five https://www.tadbirnet.ir/portfolio/project-five-2/ https://www.tadbirnet.ir/portfolio/project-five-2/#respond Sun, 31 Mar 2019 19:35:44 +0000 https://www.tadbirnet.ir/?post_type=portfolio&p=1419 Objectives of the project: Phase 1: Handling 50,000 barrels of oil and injected 70 million cubic feet of gas a day Phase 2: Achieve 110,000 barrels of oil and inject 210 million cubic feet of gas a day Geographical location of the project: km north of Khorramshahr and 100 km southwest of Ahwaz, along the […]

The post Project five appeared first on طراحی سایت | سئو و بهینه سازی سایت | سامانه پیامکی|تدبیرنت.

]]>
slide-2feca5b
slide-f145459
slide-444258c
slide-f4fec89

Objectives of the project:

Phase 1: Handling 50,000 barrels of oil and injected 70 million cubic feet of gas a day

Phase 2: Achieve 110,000 barrels of oil and inject 210 million cubic feet of gas a day

Geographical location of the project:

km north of Khorramshahr and 100 km southwest of Ahwaz, along the Ahwaz-Khorramshahr road

main contractor:

Phase 1 and 2 ENI / NICO

Project Implementation Activities:

Drilling of 3 wells and 5 wells and one well gas injection well The creation of a unit of operation with a nominal capacity of 55 thousand barrels per day All pipelines and pipelines in the first phase of the project Drilling 15 development loops, 3 gas injection wells and one wells water disposal Zayed, along with the creation of a unit of operation with a nominal capacity of 165 thousand barrels of oil On the day, including all lines of flow and well-developed facilities in the second phase

– Feasibility Study Phase III was conducted by ENI

– Define the descriptive stage of the design and preparation of documents for this part of the work using internal resources

Key layout times:

Date of Contract Entry: April 13,

Production of 50,000 barrels per day will be achieved on August 83

Production forecast reached 160 thousand barrels per day: September, 2002

Forecast of gas injection at 280 million cubic feet per day: Spring 2010